search

 THE HONG KONG INSTITUTE OF SURVEYORS PQSL (23 NOVEMBER 2002) PRE ...

0 comments

file time: 2008-02-16

filetype:ppt

Click Here To Download...

>  

23 November 2002  

By Sunny Chan and Stephen Wong  

THE HONG KONG INSTITUTE OF SURVEYORS

JUNIOR ORGANISATION 00PQSL SERIES

(23 NOVEMBER 2002) 

By

Sunny Chan, AHKIS, MRICS

Stephen Wong, AHKIS, MRICS 

PRE-CONTRACT CONSTRUCTION

COST ESTIMATING

 

23 November 2002  

By Sunny Chan and Stephen Wong  

CONTENTS 

PART 1 -  TERMS AND DEFINITIONS

(A) Area Classification

(B) Terms used in Cost Estimate and Cost Analysis 

PART 2 -  TYPE OF COST ESTIMATE

(A) The Pre-Contract Cost Estimating Process

(B) Rough Indication of Costs/ Indicative Order of Costs

(C) Preliminary Cost Estimate

(D) Detailed Cost Estimate

(E) Pre-Tender Estimate

(F) Reconciliation of Estimate

(G) Cost Studies of Alternatives 

PART 3 -  IMPORTANT POINTS FOR COST ESTIMATING

(A) Pricing of Cost Estimate

(B) Verification of Quantities

(C) Accuracy of Cost Estimate 

PART 4 -  QUESTION AND ANSWER 

 

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 1 00TERMS AND DEFINITIONS 

(A) Area Classification

(B) Terms used in Cost Estimate and Cost Analysis

 

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 1 00TERMS AND DEFINITIONS 

(A)  AREA CLASSIFICATION 

GROSS FLOOR AREA (GFA) of a building is the area contained within the external walls of the building measured at each floor level, together with the area of balcony and the thickness of external walls, but excluding carpark and plant room areas.  (for submission to Planning Authorities) 

CONSTRUCTION FLOOR AREA (CFA) is the covered areas fulfilling the functional requirements of the building measured to the outside face of the external walls or external parameter, and measured over lift shaft voids and stair well, inclusive of bay window, carpark and mechanical room and open covered areas. 

LETTABLE AREA is the area which could be leased to a tenant for his exclusive use.  Measurement should include half of the thickness of walls enclosing the lettable area.  (for feasibility studies to assess the profitability) 

USABLE FLOOR AREA is the floor area other than staircases, staircase halls, lift landings, area for sanitary wares and area occupied by lift and machinery .  (for submission to Planning Authority) 

 

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 1 00TERMS AND DEFINITIONS 

(B)  TERMS USED IN COST ESTIMATE AND COST ANALYSIS 

ELEMENT QUANTITY is the quantities of element based on element unit, e.g. room, door, wall finishes, etc. 

ELEMNET RATIO is the element quantity per unit CFA (i.e Element Quantity / CFA) 

ELEMENT UNIT RATE is the average cost per unit element quantity.  (Thus, Total Cost of Element / Element Quantity) 

INDICES are the indication of price level for particular subject, such as tender price index, building services tender price index, labour index, material index and consolidated labour & material index. 
 
 
 
 

 

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 2 00TYPE OF COST ESTIMATE 

(A) The Pre-Contract Cost Estimating Process

(B) Rough Indication of Costs/ Indicative Order of Costs

(C) Preliminary Cost Estimate

(D) Detailed Cost Estimate

(E) Pre-Tender Estimate

(F) Reconciliation of Estimate

(G) Cost Studies of Alternatives

 

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 2 00TYPE OF COST ESTIMATE 

(A)  THE PRE-CONTRACT COST ESTIMATING PROCESS (General Concept) 

Preliminary Cost Estimate (Elemental form based on elemental unit costs) 

Schematic design drawings showing general layout, shape and height of building.

Form of construction 

Prepare cost estimate & initial cost studies in order to check & confirm cost limit/ budget. 

Outline Proposal 

Pre-Tender Estimate

(Based on BQ priced with current prices) 

Complete design & working drawings and specifications. 

Cost check of final design 

Tender 

Comparative Cost Studies

(Reconciliation of costs and cost studies of alternative) 

Alternative design proposal.

Design development 

Update cost and further cost studies of design alternatives 

Design Development 

Detailed Cost Estimate

(Elemental form based on approximate quantities priced at current rates) 

Architectural plans, elevations & sections

Structural framing plans

Foundation information

Standard of finishes

Building Services 

Prepare cost plan & continue cost studies of alternative to check & confirm cost limit/ budget. 

Scheme Design 

Rough Indication of Costs/ Indicative Order of Costs

(GCFA  x HK$/m2) 

Location and area of the site

Project Details, e.g. GFA/GCFA, height, size, use and programme

Quality standard required 

Prepare feasibility studies to determine the cost limit/ budget. 

Inception & Feasibility 

Type of Cost Estimate 

Information of Available 

Main Purposes 

Stages

 

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 2 00TYPE OF COST ESTIMATE 

(B)  ROUGH INDICATION OF COSTS/ INDICATIVE ORDER OF COSTS 

Total Costs = Construction Floor Area (CFA) x Unit Area Cost (HK$/CFA) 

Where,

CFA can be estimated based on the following information:- 

Land & development conditions (e.g. site area, plot ratio, site coverage, height limitation and gross floor area) 
Maximum buildable area = site area x approved plot ratio 
Approx. CFA = site coverage area x no. of floor (for building with full site coverage) 
Approx. CFA = GFA x conversion factor (1.05-1.10 for residential, 1.10-1.20 for office)  
Functional parameters [e.g. hospital (60m2 to 120m2 per bed), hotel (55m2 to 100m2 per room), auditorium (1.5m2 to 2m2 per seat) and carpark (30m2 to 40m2 per carpark)] 

Unit Cost can be built up by :- 

Reference to the Cost Analysis of the previous similar projects; and Adjustment of price level, location factor, quality of standard, physical conditions, construction methods and other particulars.  

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 2 00TYPE OF COST ESTIMATE 

(C)  PRELIMINARY COST ESTIMATE 

Total Construction Costs = Sum of (Elemental Quantity x Elemental Unit Rate) 

In Elemental Form.  It include the elements of demolition & alteration, site investigation, site formation, foundation, substructure & basement, structural frame, roof covering, external facade, internal partition & door, internal finishes, fitting & fixture,  interior decoration, building services, landscaping, external works, preliminaries and contingencies. 

Elemental Quantity can be obtained either from the design information of the proposed project or the cost analysis of previous similar projects. 

Elemental Unit Rate can be estimated from the Cost Analysis of the previous similar projects; and with adjustment of price level, location factor, quality of standard, physical conditions, construction methods and other particulars.  

Allowance of Preliminaries and Contingencies 

The report of preliminary cost estimate consists of cover, contents, summary of estimated costs, scope of cost estimate (inclusion & exclusion), general particulars (project details, definition of area, schedule of area & basis of cost estimate), outline specification and assumptions and supplementary information.

 

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 2 00TYPE OF COST ESTIMATE 

(D)  DETAILED COST ESTIMATE 

Total Construction Costs = Sum of (Approximate Quantity x Unit Rate) 

In Elemental Form. It include the elements of demolition & alteration, site investigation, site formation, foundation, substructure & basement, structural frame, roof covering, external facade, internal partition & door, internal finishes, fitting & fixture,  interior decoration, building services, landscaping, external works, preliminaries and contingencies. 

Approximate Quantity for each element can be measured based on the design information (including drawings and specifications). 

Unit Rate can be estimated from the Cost Analysis of the previous similar projects with appropriate adjustment, (ii) recent returned tenders, (iii) recent prepared cost estimate, and (iv) supplier00/sub-contractor00 quotations. 

Allowance of Preliminaries and Contingencies. 

The report of detailed cost estimate consists of cover, contents, summary of estimated costs, scope of cost estimate (inclusion & exclusion of works), general particulars (project details, definition of area, schedule of area and basis of cost estimate), outline specification and assumptions and supplementary information.

 

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 2 00TYPE OF COST ESTIMATE 

(E)  PRE-TENDER ESTIMATE 

Prepared based on the bills of quantities measured from the tender/working drawings. 

Priced at the current rate which can be obtained from

the Cost Analysis of the previous similar projects with appropriate adjustment, recent returned tenders, recent prepared cost estimate, supplier00/sub-contractor00 quotations.  

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 2 00TYPE OF COST ESTIMATE 

(F)  RECONCILIATION OF ESTIMATE 

Reconciliation of Cost Estimate is used to systematically report the cost change/ difference between the old cost estimate and the new cost estimate.  Therefore, the reasons of the change/difference can be identified and assessed. 

The cost difference is usually due to (i) change in price level, (ii) change in the Employer00 requirement, (iii) change in design/development, (iv) more advanced information obtained, (v) change in site conditions, and (vi) adjustment upon awarded contract. 

It is particularly useful for proceeding cost saving exercise and reporting changes of the project. 

Upon necessary, it may be required to carry out at each pre-contract stage. 

 

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 2 00TYPE OF COST ESTIMATE 

(G)  COST STUDIES OF ALTERNATIVES 

Cost studies is to compare two alternatives of design scheme/requirements in terms of cost consideration.  It provides a clear cost direction for the client/architect to make their final decisions on the selection of design schemes. 

Particular in Value Engineering studies and can be applicable to each pre-contract stages.

 

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 3 00IMPORTANT POINTS  
FOR COST ESTIMATING 

(A) Pricing of Cost Estimate

(B) Verification of Quantities

(C) Accuracy of Cost Estimate

 

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 3 00IMPORTANT POINTS FOR COST ESTIMATING 

(A)  PRICING OF ESTIMATE 

Use of Composite Rates and Lump Sum Allowances  
Source of Prices can be obtained from/ cross-checked by (i) suppliers/sub-contractor00 quotations, (ii) recently returned tenders, (iii) recently prepared estimates, (iv) historical cost data/ cost analysis.  
Particular attention to be drawn on price level, market conditions, location of site, site conditions, programme of work, procurement method, contract conditions, size of the project and other special characteristics.  

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 3 00IMPORTANT POINTS FOR COST ESTIMATING 

(B)  VERIFICATION OF QUANTITY  

The quantity of each element should be checked and verified whether it is reasonable.  The following are some of the common ratio/proportion for verification of the element quantity. 

CFA / no. of H-pile  and CFA/ sectional area of bored pile  
Reinforced concrete / CFA  
Formwork / CFA  
Reinforcement / CFA  and Reinforcement / reinforced concrete  
(External wall finishes + windows + curtain wall) / CFA  
Roof waterproof = largest footprint  
Floor finishes = Approx. 90% CFA  
Internal wall finishes / CFA  and Internal ceiling finishes / Total floor finishes  

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 3 00IMPORTANT POINTS FOR COST ESTIMATING 

(C)  ACCURACY OF ESTIMATE 

Client00 brief  
Availability of Information  
Market condition/inflation  
Method of estimating  
Site conditions  
Tendering procedure and contractual arrangement  
Uniqueness of project  
Experience of estimator  

23 November 2002  

By Sunny Chan and Stephen Wong  

PART 4 00QUESTION AND ANSWER 

Q & A

 

23 November 2002  

By Sunny Chan and Stephen Wong  

-  END OF PRESENTATION  -

   download THE HONG KONG INSTITUTE OF SURVEYORS PQSL (23 NOVEMBER 2002) PRE ...

Responses to THE HONG KONG INSTITUTE OF SURVEYORS PQSL (23 NOVEMBER 2002) PRE ...

It's no comment...

 

Your Name:
Your Email:
Your Talk: