Pre-Qualification Structured
Learning (PQSLs) Series 00
Schedule of Rates
vs.
Bills of Quantities
The Hong Kong Institute of Surveyors
Date: 22 March 2003 [2:00 p.m. to 4:00 p.m.]
By: Mr. Y.C. Chan
Why Use Bills of Quantities
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
describing the full requirements in the
drawings and specifications.
rates to provide a list of rates
for the valuation of variations purpose.
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
the contract.
a) buildup the tender/contract sum.
b) provide a list of rates for the valuation of variations purpose.
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
1 Agreement & Schedule of Conditions of Building Contract for use in Hong Kong
(Standard Form of Building Contract) Private Edition
a) - With Quantities
b) - Without Quantities
2 General Conditions of Contract for E & M Engineering Works (1999 Edition)
3 General Conditions of Contract for Civil Engineering Works (1999 Edition)
4 General Conditions of Contract for Design and Build Contract (1999 edition)
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
1a Standard Building Contract (With
Quantities)
In 00rticles
of Agreement00which stated 0000Drawings and Bills
of Quantities showing and describing
the works to be done to be prepared
000
Clause 12 (1)
The quantity and quality of the work included in the Contract Sum shall be deemed to be that which is set out in the Contract Bills which Bills unless otherwise expressly stated in respect of any specified item or items shall be deemed to have been prepared in accordance with the principles of the Standard Method of Measurement of Building Works for use in Hong Kong 00/font>
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
1a Standard Building Contract (With
Quantities)
Any error in description or in quantity in or omission of items from the Contract Bills shall not vitiate this Contract but shall be corrected and deemed to be a variation required by the Architect
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
1b Standard Building Contract (Without
Quantities)
In 00rticles
of Agreement00which stated 0000Drawings and a Specification marked
0000showing and describing the works to be done to be prepared 000
The quantity and quality of the work included in the Contract Sum shall
be deemed to be that which is shown upon the Contract
Drawings or described in the Specification,
00/font>
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
1b Standard Building Contract (Without
Quantities)
The term 00ariation00
as used in these Conditions shall means the alteration or modification
of the design, quality or quantity of the Works as shown upon the Contract Drawings and described by or referred to in the Specification 00/font>
Any error in description or in quantity in or omission of items from the Contract Drawings and/or the Specification shall not vitiate this Contract but shall be corrected and deemed to be a variation required by the Architect
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
2 General Conditions of Contract
for E & M Engineering Works (1999 Edition)
00ontract00 means the Articles of Agreement, the Tender and the acceptance thereof by the Employer, 00rawings, General Conditions of Contract, Special Conditions of Contract (if any), Specification and priced Schedule of Quantities or Schedule of Rates.
.
Clause 59 (1)
The quality and quantity of work included in the Contract Sum is deemed to be that which is shown on the Drawings or described in the Specification. The Contractor shall be deemed to have ascertained the exact quantities before submitting his Tender.
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
2 General Conditions of Contract
for E & M Engineering Works (1999 Edition)
When a Schedule of Quantities is included in the Contract, any error in description or any error in the quantities entered therein or any item omitted therefrom shall not vitiate the Contract nor release the Contractor from the execution of the whole or any part of the Works according to the Drawings and Specification or from any of his obligations or liabilities under the Contract. Only provisional quantities and the quantities for any variation ordered in accordance with Clause 60 shall be remeasured.
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
2 General Conditions of Contract
for E & M Engineering Works (1999 Edition)
There shall
be no rectification of any error, omission or wrong estimate in
description, quantity or rate inserted
by the Contractor in the Schedule
of Quantities or Schedule of Rates.
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
3 General Conditions of Contract
for Civil Engineering Works
00ontract00
means the Articles of Agreement, the Tender and the acceptance thereof
by the Employer, Drawings, General Conditions of Contract, Special Conditions
of Contract if any, Specification and priced
Bills of Quantities.
"Contract
Sum" means the total of the Priced Bills
of Quantities at the date of
the acceptance of the Tender.
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
3 General Conditions of Contract
for Civil Engineering Works
00work shown on the Drawings or described in the Specification but not measured in the Bills of Quantities shall be dealt with in accordance with Clause 59;
Clause 59 (1)
Except where any statement in the Bills of Quantities expressly shows to the contrary the Bills of Quantities shall be deemed to have been prepared and measurements shall be made according to the procedures set forth in the Method of Measurement stated in the Preamble to the Bills of Quantities.
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
3 General Conditions of Contract
for Civil Engineering Works
Should the actual quantity of work executed in respect of any item be substantially greater or less than that stated in the Bills of Quantities (other than an item included in the daywork schedule if any) and if in the opinion of the Engineer such increase or decrease of itself shall render the rate for such item unreasonable or inapplicable, the Engineer shall determine an appropriate increase or decrease of the rate for the item using the Bills of Quantities rate as the basis for such determination and shall notify the Contractor accordingly.
Differences between
Bills of Quantities (BQ) and Schedule of Rates (SoR)
4 General Conditions of Contract
for Design and Build Contract (1999 edition)
Clause 1
"Contract"
means the Articles of Agreement, the Tender and the acceptance thereof
by the Employer (including such further agreed documents as may be expressly
referred to in or by the same), General Conditions of Contract, Special
Conditions of Contract (if any), Employer's Requirements and Contractor's Proposals.
"Contract Sum" means the sum referred to in the Contractor's Proposals at the date of the acceptance of the Tender for the execution of the Works.
How to choose : BQ or
SoR ?
I.
Type of Conditions of Contract (CoC)
(1986, 1st Ed, second amendments published July 1999)
Building Contract without Quantities
(1986, 1st Ed, second amendments published July 1999)
General Conditions of Contract for Civil Engineering Works (1999 edition)
General Conditions of Contract for E & M Engineering Works, (1999 edition)
General Conditions of Contract for Design and Build Works (1993 edition)
How to choose : BQ or
SoR ?
II.
Type of Works
How to choose : BQ or
SoR ?
III.
Design Requirements in the Contract
What is the extent of the design requirement?
How to choose : BQ or
SoR ?
IV. Size of the Contract
Small size contract 00/font>- Simple
- Small variances in contract sum
- Short contract period
- Complicated
- Exposed to more possible variances in contract sum
- Longer contract period
How to choose : BQ or
SoR ?
V.
Pre-contract Preparation Time Limit
- Take longer preparation time for all consultants
- Usually based on drawings not fully detailed.
- The time required is usually shorter.
Questions and Answers